Flooring is hard and dirty work
Flooring is hard work. I honestly though that three days over the memorial weekend would be enough to get the floor down. I’d already pulled up all the old boards, so all we had to do was repair the termite damaged sub floor and lay the oak.
The sub floor was worse then I’d expected – although not as bad as it could have been. When I first started pulling up the old fir, it looked as though most of the sub floor had been chewed up. I honestly though I was going to have to replace the whole lot – although that may have worked out faster. In the end we had to replace about 240 linear ft of the 1*6. I’d arranged for a friend of mine to come over and help and even with the two of us it still took Saturday and Sunday to get the repairs done.
Here’s the dining room after repair:

And looking towards the living room:

Most of the corner under the pile of floor boards was replaced. You can tell the new boards by their color.
The three tenets of a good builder are Plumb, Level and Square. Level is a bit much to hope for in a 90 year old house, so we settled for flat. Monday morning saw us crawling around the floor with a straight edge checking that variances didn’t exceed an 1/8th inch over 6ft. We got lucky.
Next up was laying roofing paper to absorb the squeaks and any minor variances.

We decided on a double width for the transition between the main run and the fireplace hearth. The rooms are long and narrow, so the boards have to run long ways or else you end up with the “ladder” effect. The transition breaks the line of the boards running to the hearth, and defines the border between the floor and the hearth
Here’s the first board laid down. You can also see the chalk reference lines

I don’t have a picture of it, but the next step was to run two long runs of boards from the hearth to the window seat in the dining room. These runs are “groove to groove” with a slip tongue joining them. This allows the floor boards to run in two opposite directions which will make things a lot easier once we get to the columns.
By this point it was about 3:00pm on Monday afternoon.
This is where we got to at 9:00pm Monday:

The two “back to back” runs are on the left. Things definitely progressed faster once we had everything snapped out and were just laying the boards. In case you’re wondering, the string hanging from the dining room light fixture is to help us avoid the pointy bit. Its hard to avoid obstacles above you when your attention is focused on the floor.
Here are a couple of better photos taken this morning:


I really like the color of the floor. Its almost a shame that we have to refinish it.
I’ve still got to post pictures of the shed. Hopefully this weekend.